Skip to content
Design and Specification  |  Standards and Regulations  |  Technical

The legalities behind specifications

04 March 2017 | By Sarah Wilson and Bal Manak

Sarah Wilson and Bal Manak, from Construction Law firm Watson Burton LLP, explore the role of a specification as part of a construction contract.

Diagram

The majority of respondents to the NBS specification survey told us that they have experienced difficulties when producing or using specifications. Not all of these difficulties will result in disputes, but some might. In fact, in 2015, 44% of those responding to the NBS Contracts and Law survey had to deal with at least one dispute within the last year. Here we explore the role of a specification as part of a construction contract.

The fundamentals

A construction contract will usually be made up of the following documents:

  1. The contract (legal document).
  2. The terms and conditions (legal document).
  3. The specification (technical document).
  4. Ancillary documents, such as collateral warranties, bonds, parent company guarantees (legal documents).

These documents work hand-in-hand and are all legally binding. The specification states what the contractor builds, whilst the terms and conditions address what happens if the work does not go to plan (for example, defects, delays, variations). Here are some good and very simple examples of how these documents operate in practice:

  1. Variation payments to a contractor – if the specification changes at the request of the employer, the terms and conditions will usually require the employer to pay the Contractor for this.
  2. The specification will usually state the tests that the employer wishes to carry out and when. Failure to comply with this requirement will usually mean that the Contractor is entitled to additional payment via the terms and conditions.

Typically you would expect to see a clause (in the terms and conditions) specifying the priority of each of the documents, and usually they would be in the order as set out above. The purpose of this is to deal with any ambiguities within the documents or between them.

When negotiating contract terms and conditions for a client, we always prefer to see any specification. This avoids any items being included in the specification which conflict with those being negotiated elsewhere by the lawyers.

Potential issues which can arise from a specification are:

  • Incomplete or ambiguous terms.
  • Duplication or contradiction of contract terms and conditions.
  • Incorrect terminology and referencing (such as JCT-type specification used for NEC project)
  • Specifications drafted from ‘scratch’ (which risks something being missed) or cut and pasted from other specifications.
  • Specifications prepared without reference to contract guidance notes on what the specification should include.

“In practice, the Brief is often a working document which is developed by the Architect/ Consultant to produce a fully compliant and tested design.”

What information should the specification contain?

The specification should include technical information on what the Contractor is required to provide, including measurements, quality, requirements to work with others, plans and drawings.

Different forms of construction contract require different information to be provided in the specification, and examples are set out below.

NEC3

The NEC form of contract includes a specification as the Works Information (‘WI’). WI is defined as:

“... information which either

  • specifies and describes the works; or
  • states any constraints on how the Contractor provides the works; and is either
  • in the documents which the Contract Data states it is in; or
  • in an instruction given in accordance with this contract”.

The WI will often be an extensive document, and some of the key issues to be covered within it are:

  1. Description of Works – a general outline of the scope of the works to be done. This may include the Employer’s overall objectives so that the Contractor can understand and work towards these.
  2. General constraints on providing the works – any restrictions on access, sequences of construction, working hours, etc.
  3. Contractor’s design – identifies the works that the Contractor is to design. The Employer’s requirements should be set out (for example specifications, design standards and codes of practice, size and space limitations).
  4. Completion – states clearly and unambiguously what work is to be done before Completion so that the project manager can decide that Completion has occurred. Alternatively, a statement identifying works which can remain incomplete at Completion.
  5. Tests and inspection – which tests and inspections are required, who is to be involved in the process, and who is to provide the materials, facilities and samples.
  6. Health and Safety – any health and safety requirements for the project, in addition to the requirements of the law.
  7. Subcontracting – any restrictions on the Contractor’s ability to subcontract work.

JCT

The specification for JCT is known as the Employer’s Requirements (‘ER’). The ER provides a description of the client’s requirements formed from the specification for the building, the scope of services required, and an allocation of risk for unknown items. The Contractor then prepares the Contractor’s Proposals in response, detailing how the building will be designed and constructed in accordance with the ER.

The JCT contracts do not prescribe what must be included in the ER, but the Contractor must comply with it, so it is important that it is drafted with care. It is also important that any inconsistencies between the ER and the Contractor’s Proposals are negotiated, and the relevant specification amended to incorporate these negotiations. Once the contract has been entered into, it is not clear which document takes priority, so there should be no discrepancies between them.

The ER may only contain basic information which the Contractor is to develop in its Contractor’s Proposals, or it may be very detailed, leaving little scope for change in the Contractor’s Proposals. Nevertheless, the more prepared, clear and precise it is, the less likely it is that there will be disputes. There will be less room for disagreement over what the Contractor was instructed to do, and it will be less likely that the employer will have to instruct a Change on the basis that it is not clear whether the additional work that the Contractor was instructed to do was part of its original scope or not. The ER is therefore a fundamental document, and employers are advised to seek the assistance of a qualified project manager to help them to draft this.

Consultants' forms of appointment, such as RIBA, ACE

The principles regarding the status of the specification in a consultant’s appointment are not dissimilar to those contained in construction contracts.

In the RIBA and ACE appointment forms, it is known as a ‘Brief’ which describes the Client’s requirements, supported by other information and drawings. In practice, the Brief is often a working document which is developed by the Architect/Consultant to produce a fully compliant and tested design. In addition, the Brief is accompanied by a ‘schedule of services’ setting out, in more detail, those services which the Architect/ Consultant is to provide.


In summary, therefore, the specification is a key document in the construction process. Where it is included as a contract document, it has legal status, and is critical to the success or failure of the project. It is clear that the specification should not be ignored, or the consequences could be severe.

The Report of the Independent Inquiry into the Construction of Edinburgh Schools, published on 9th February 2017, makes this plain: the Report was commissioned by the City of Edinburgh Council following the collapse of a wall at Oxgangs Primary School and the subsequent closure of 17 schools. One of its principal recommendations is that compliance with the specification should be ensured. Further details of the report can be found at www.edinburgh.gov.uk.

This article is taken from the NBS Specification Report 2017. Find out more and download the full free report including comprehensive analysis of our survey results.

Back to knowledge

You may also like

Three people speaking at a conference Marketing  |  Sales  |  Standards and Regulations  |  Technical

What is The Golden Thread?

12 March 2020

In the construction and architectural field, there's a lot of discussion around the 'golden threa...

illustration RIBA CPD  |  Sales

It’s all about trust

28 September 2020

Anna Hern, Managing Director at Ridgemount PR, shares her opinion with us, on CPD and how manufac...

See all knowledge

Sign Up for updates from NBS

Get the very latest from NBS, including news, event and webinar invites, support and our monthly manufacturer newsletter straight to your inbox.

NBS will use this information to contact you about the requested services and relevant communications. You can unsubscribe at any time.

This site is protected by reCAPTCHA and the Google Privacy Policy and Terms of Service apply.